The calendar and governance shape the review
Decision pointSchoolChurch / worship property
Activity recordAcademic, summer and evening programsServices, weekday programs and events
Peak investigationActual equipment and event intervalsActual equipment and event intervals
AuthorityDistrict, board or account ownerBoard, trustees or account owner
Performance contextAppropriate school methodologyAppropriate worship methodology

Build an operating calendar for the property

For a school, record the academic year, summer programs, evening activities, food service and any athletic facilities. For a church or other worship property, record services, weekday offices, childcare, community events and kitchens where present. Do not assume a worship building is occupied only once a week or that a school closes entirely in summer.

Identify separate meters, shared campuses and landlord or district-paid systems. A classroom wing and a sanctuary can have very different area and schedule boundaries. Whole-property comparisons should include all relevant energy and matching gross area, while partial accounts should remain clearly labeled.

Inspect schedules without compromising required use

Compare actual interval data with the calendar to identify questions about equipment run time and base use. A control schedule may deserve review when the building is vacant, but changes must preserve required ventilation, temperature, equipment and program conditions. This page does not prescribe universal setbacks or safety-related settings.

Demand can reflect a short interval rather than the entire monthly attendance pattern. Event preparation or simultaneous equipment starts may affect a peak, but the actual tariff and interval evidence are needed. A low annual kWh total alone does not prove a small demand charge or show that a generic load reduction will save money.

Hypothetical event-peak comparison

Suppose two properties each use 20,000 kWh in a billing period. One records 80 kW billed demand and the other 140 kW. At an invented $10 per kW charge, demand costs are $800 and $1,400. The $600 gap exists even though total energy is identical.

These are hypothetical quantities and not school or worship benchmarks. The higher peak might reflect a different event or equipment mix, not poor management. Compare like periods and identify the cause before proposing controls. A supplier rate change would address a separate component and should not be credited with reducing the physical peak.

Match procurement governance and duration

Confirm who can authorize the account, whether board or district approval is needed and how the supply term aligns with budgets and facility plans. Collect existing agreements and notice dates early enough for the actual decision process. A quote expiry does not override the organization’s authorization requirements.

Request comparable offers for eligible accounts and retain the price scope, fees and accepted documents. For performance, use appropriate school or worship benchmarking context instead of ranking unlike services by a single area ratio. This guide promises no nonprofit discount or standard savings percentage; it helps organizations compare calendar-driven loads and purchasing responsibilities with actual evidence.

Questions & answers

Does nonprofit status guarantee a cheaper supplier rate?

No general discount is established here. Verify any specific program or offer and compare its complete terms.